Swing Bridge bypass has four spans in place

Newsroom brief · Based on the linked report
Chief Engineer Evondale Moody puts the crossing under construction near Belize City’s Swing Bridge at 75 to 80 percent complete, Love FM reports. Four of its five spans are in place. Crews are working on the approaches, while utility teams need to reroute a fibre line and relocate a power pole. Moody is aiming for completion in late November or early December. The crossing will have two lanes and footpaths on both sides.
Why it matters: Work near North Front Street and Regent Street West can slow trips downtown. The completion window is an estimate, so commuters should check current traffic notices.